‘Box structure’ flyover saves £70m and six months for East West Rail
Engineers have saved £70m of taxpayers’ money by using creative new methods to build a railway flyover as part of the East West Rail project.
Network Rail and the East West Rail Alliance are restoring the Oxford-to-Cambridge line by removing and replacing a flyover which crosses the busy West Coast main line at Bletchley – all while keeping trains and passengers moving safely.
The new structure, on the line between Bicester and Bletchley, is being built to last 120 years with minimal future maintenance required.
Instead of replacing the old flyover like-for-like – which would involve closing the West Coast main line below to build five supporting columns in between the tracks – East West Rail project engineers have used modern methods of construction to build a protective ‘box structure.’
It acts very much like a rectangular railway tunnel, removing the need for separate supporting columns and providing a platform for the flyover to sit on.
This means the West Coast main line – which is one of the busiest mixed-use passenger and freight railway routes in Europe – doesn’t have to be closed during the flyover replacement taking place above as the box structure provides a protective, physical barrier.
This keeps both passenger and freight trains safe below and the workforce safe above.
Mark Cuzner, East West Rail Alliance project director, said: “By working smarter we’ve been able to speed-up the project by around six months. At the start of the project, we built a protective wall next to the West Coast main line so we could safely build the box structure during the day when the railway is open, instead of working piecemeal at night-time when the railway is closed.
“Most of the components for both the box structure, and the flyover, arrived pre-built and were simply assembled on site, like a model kit or set of Duplo bricks. The simplicity of construction meant we could safely reduce the workforce onsite by 60%, cut the previously-forecast cost by £70m and get the job done six months quicker than planned.”
Simon Blanchflower CBE, East West Rail Company chief executive officer, said: “The transformation of the iconic Bletchley flyover has really brought the East West Rail project to life and brings communities from Oxford to Cambridge ever closer to a new, sustainable transport link across the region”
Key figures from this innovative construction technique include:
- £70m saved by reducing the need to close the railway
- Modern methods of construction speeds-up project by six months
- 70% of components arrived pre-built and were simply assembled on site
- Simplicity of construction meant onsite workforce could be reduced by 60%
- New flyover will last 120 years (previous one lasted only 60 years)
In the coming months track will start to be laid over the new structure.
It replaces a 1960s-built concrete railway flyover which wasn’t suitable to carry the new East West railway.
The huge demolition project on the old structure took place throughout 2020 and involved some of the UK’s largest cranes.
For more information on the East West Rail project visit: www.networkrail.co.uk/east-west-rail/
More in Public Transport
Unipart Company, Park Signalling, Secures £3M Network Rail Contract
Unipart company Park Signalling has kicked off 2025 with a significant achievement in the rail industry, securing a £3m contract with Network Rail. This major milestone reinforces Unipart’s reputation as a leading provider of cutting-edge technology solutions and its commitment to advancing the efficiency, safety, and sustainability of the UK’s rail network.
Pioneering US-based Canoo Inc’s versatile electric vehicle experience arrives at Bicester...
Canoo Inc, a US-based company which has created revolutionary multi-purpose platforms and digital ecosystems that are transforming the automotive industry for the entire vehicle lifecycle, has selected Bicester Motion, the 444-acre future mobility estate in Bicester, Oxfordshire, as its UK commercial operations and activation centre.
Oxford Brookes hosts event looking at the future of autonomous transport
The future of transport and the challenges facing the development of smart, connected and autonomous vehicles was discussed at a two-day event at Oxford Brookes University earlier this month.
From this author
Enjoy a Delightful Networking Opportunity at the February B4 Members Lunch
Date: February 2025
Location: Hilton Garden Inn, Abingdon Oxford
Exciting January Events for B4 Members: A Great Start to 2025
January 2025 promises an exhilarating line-up of events for B4 Members, offering opportunities to connect, celebrate, and be inspired. With three unique gatherings, B4 Members can look forward to forging meaningful connections, experiencing rich cultural traditions, and engaging with influential figures in the local community. Here’s a closer look at what’s in store:
Will UK House Prices Rise in 2025? An Economic Perspective by...
The UK housing market is poised to face a confluence of challenges and opportunities in 2025. As highlighted by James Sproule, UK Chief Economist at Handelsbanken, several key factors—wealth, supply and demand, affordability, and investment yield—are instrumental in shaping house prices. These dynamics, coupled with broader economic trends, will influence how the housing market evolves in the coming year.